It has been determined through careful analysis that Task A has a CPI of 1.04 and a SPI of .93. Explain in simple terms what is happening with Task A.

Construction project cost analysis

It has been determined through careful analysis that Task A has a CPI of 1.04 and a SPI
of .93. Explain in simple terms what is happening with Task A.
2. Large separations between ACWP and BCWP on the S-curve may be indicators of what?