Operations and Supply Chain Management Assignment
Project ABC consists of the following four activities with activity times in days:
Activity Predecessor Time
A 6
B A 5
C A 4
D B,C 8
What is the critical path for Project ABC?
According to your identified critical path, the time to complete the entire project is how many days?